6201 W HOLLYWOOD BLVD 90028
APPLICATION / PERMIT NUMBER: 07020-10000-04633
PLAN CHECK / JOB NUMBER: B07LA12082

Plan Check and Permit Information


GROUP: Building
TYPE: Nonbldg-New
SUB-TYPE: Apartment
PRIMARY USE: (23) Shoring (Temporary)
WORK DESCRIPTION: SHORING EARTH SYSTEM FOR THE CONSTRUCTION OF THE SUB-TERRANEAN PARKING FOR BUILDING UNDER PERMIT 07010-10000-04826.
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 11/29/2011 ISSUING OFFICE: Metro
CURRENT STATUS: Permit Finaled CURRENT STATUS DATE: 09/12/2013

Permit Application Status History
Submitted 11/26/2007 APPLICANT
Assigned to Plan Check Engineer 11/29/2007 RICARDO TRES
Corrections Issued 12/03/2007 RICARDO TRES
Quality Review Completed 12/05/2007 CHARMIE HUYNH
Building Plans Picked Up 12/07/2007 APPLICANT
Plan Check Approved 11/29/2011 RICARDO TRES
Issued 11/29/2011 LADBS
Permit Finaled 09/11/2013 SAKO AGHAZARIAN

Permit Application Clearance Information
Excavation more than 5-ft deep Cleared 12/07/2010 CALOSHA APPROVED
Stormwater Pollution Mitigatn Cleared 12/20/2010 AMMAR ELTAWIL
Project located in CRA area Cleared 04/08/2011 W. ONO UJOR
City hist. mon. (ZI145- <1000) Cleared 05/19/2011 LAMBERT GIESSINGER
Historic monument Cleared 05/19/2011 LAMBERT GIESSINGER
CEQA clearance Cleared 08/31/2011 BRIDGETTE WOOTEN
Grading in hillside Cleared 08/31/2011 BRIDGETTE WOOTEN
Encroachment in public way Cleared 11/10/2011 TERRY PHAN
Eng Process Fee Ord 176,300 Cleared 11/10/2011 TERRY PHAN
Miscellaneous Cleared 11/10/2011 TERRY PHAN
Work Adjacent to Public Way Cleared 11/10/2011 TERRY PHAN
Metro Rail approval Cleared 11/21/2011 ASPET DAVIDIAN
Mailing Labels Cleared 11/29/2011 RICARDO TRES

Licensed Professional/Contractor Information
Contractor Information
Benchmark Contractors Inc; Lic. No.: 462263-B
2901 28TH STREET # 150
SANTA MONICA, CA  90405
Engineer Information
Cefali, David Allen; Lic. No.: S3658
4344 LAUREL CANYON BLVD_STE 3
STUDIO CITY, CA  91604

Inspection Activity Information

Inspector Information
DAVID BURKHEAD, (213) 276-8147
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  No data available

Inspection Request History
  Pre-Inspection   04/27/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   06/29/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/02/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/03/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/05/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/06/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/09/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/10/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/11/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/12/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   07/13/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   07/13/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/13/2012   Approved   SAKO AGHAZARIAN
  Piling/Pier/Caisson   07/13/2012   Partial Approval   SAKO AGHAZARIAN
  Deputy Grading   07/16/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   07/16/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/16/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/16/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   07/17/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   07/17/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/17/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/17/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   07/18/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   07/18/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/18/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/18/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   07/19/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   07/19/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/19/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/19/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   07/20/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   07/20/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/20/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/20/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   07/23/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/23/2012   Conditional Approval   SAKO AGHAZARIAN
  Deputy Grading   07/24/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/24/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   07/25/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/25/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   07/26/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/26/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   07/27/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/27/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   07/30/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/30/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/30/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   07/31/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   07/31/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/31/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/01/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/01/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/01/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/02/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/02/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/02/2012   Approved   SAKO AGHAZARIAN
  Piling/Pier/Caisson   08/02/2012   Partial Approval   SAKO AGHAZARIAN
  Deputy Grading   08/03/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/03/2012   Conditional Approval   JOHN CARPENTER
  Deputy Reinf. Concrete   08/03/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/03/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/06/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/06/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/07/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/07/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/08/2012   Conditional Approval   JOHN CARPENTER
  Deputy Steel/Welding   08/08/2012   Conditional Approval   JOHN CARPENTER
  Deputy Reinf. Concrete   08/09/2012   Conditional Approval   JOHN CARPENTER
  Deputy Steel/Welding   08/09/2012   Conditional Approval   JOHN CARPENTER
  Deputy Reinf. Concrete   08/10/2012   Conditional Approval   JOHN CARPENTER
  Deputy Steel/Welding   08/10/2012   Conditional Approval   JOHN CARPENTER
  Deputy Grading   08/13/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   08/13/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/13/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/13/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/14/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   08/14/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/14/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/14/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/15/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   08/15/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/15/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/15/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/16/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   08/16/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/16/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/16/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/17/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   08/17/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/17/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/17/2012   Conditional Approval   SAKO AGHAZARIAN
  Deputy Grading   08/20/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/20/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/20/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/21/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/21/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/21/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/22/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/22/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/22/2012   Approved   SAKO AGHAZARIAN
  Footing/Foundation/Slab   08/22/2012   Partial Inspection   SAKO AGHAZARIAN
  Deputy Grading   08/23/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/23/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/23/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/24/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/24/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/24/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/27/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/27/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/27/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/28/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/28/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/28/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/29/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/29/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/29/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/30/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/30/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/30/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   08/31/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/31/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/31/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   09/06/2012   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   09/07/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   09/10/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/10/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/10/2012   Approved   SAKO AGHAZARIAN
  Deputy EIFS   09/11/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/11/2012   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   09/11/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/11/2012   Approved   SAKO AGHAZARIAN
  Deputy EIFS   09/12/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/12/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/12/2012   Approved   SAKO AGHAZARIAN
  Deputy EIFS   09/13/2012   Partial Approval   LESLIE TRUJILLO
  Deputy Reinf. Concrete   09/13/2012   Partial Approval   LESLIE TRUJILLO
  Deputy Shotcrete   09/13/2012   Partial Approval   LESLIE TRUJILLO
  Deputy Steel/Welding   09/13/2012   Partial Approval   LESLIE TRUJILLO
  Deputy EIFS   09/14/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/14/2012   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   09/14/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/14/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   09/17/2012   Partial Approval   LESLIE TRUJILLO
  Deputy Reinf. Concrete   09/17/2012   Partial Approval   LESLIE TRUJILLO
  Deputy Steel/Welding   09/17/2012   Partial Approval   LESLIE TRUJILLO
  Deputy Grading   09/18/2012   Partial Approval   WILLIAM GARCIA
  Deputy Reinf. Concrete   09/18/2012   Partial Approval   WILLIAM GARCIA
  Deputy Steel/Welding   09/18/2012   Partial Approval   WILLIAM GARCIA
  Deputy Grading   09/19/2012   Partial Approval   WILLIAM GARCIA
  Deputy Reinf. Concrete   09/19/2012   Partial Approval   WILLIAM GARCIA
  Deputy Steel/Welding   09/19/2012   Partial Approval   WILLIAM GARCIA
  Deputy Grading   09/20/2012   Partial Approval   JAMES POWERS
  Deputy Reinf. Concrete   09/20/2012   Partial Approval   JAMES POWERS
  Deputy Steel/Welding   09/20/2012   Partial Approval   JAMES POWERS
  Deputy Grading   09/21/2012   Partial Approval   LESLIE TRUJILLO
  Deputy Reinf. Concrete   09/21/2012   Partial Approval   LESLIE TRUJILLO
  Deputy Steel/Welding   09/21/2012   Partial Approval   LESLIE TRUJILLO
  Deputy Grading   09/24/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/24/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/24/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   09/25/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/25/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/25/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   09/26/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/26/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/26/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   09/27/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/27/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/27/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   09/28/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/28/2012   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/28/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/01/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/02/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/03/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/04/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/05/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/09/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/10/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/11/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   10/11/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/12/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/15/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/16/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/17/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/18/2012   Approved   SAKO AGHAZARIAN
  Deputy Grading   10/19/2012   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   11/07/2012   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   11/08/2012   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   11/09/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   11/19/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Masonry   11/19/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   11/20/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Masonry   11/20/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   11/21/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Masonry   11/21/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Masonry   11/27/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Masonry   12/07/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   12/10/2012   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   01/23/2013   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   01/25/2013   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   02/25/2013   Approved   SAKO AGHAZARIAN
  Final   09/11/2013   Permit Finaled   SAKO AGHAZARIAN
  SUSMP-Std. Urban Storm Water   09/11/2013   Approved   SAKO AGHAZARIAN